Contractor was tying rebar when I arrived, had him move the footing steel to line up with existing wall better.
Concrete arrived at 1:40, I tested the concrete: Slump 41/2", Air 5%, Temp 80°. I made 3 cylinders out of each truck. Pour went good, started raining on the last truck.
Concrete arrived at 1:40, I tested the concrete: Slump 41/2", Air 5%, Temp 80°. I made 3 cylinders out of each truck. Pour went good, started raining on the last truck.