Site visit, Poured Wing Walls
Contractor was finishing up Forms when I arrived onsite. Concrete arrived at 9, I tested the concrete: Slump 4", Air 6%, Temp 64°. I made three cylinders Started wall 2 Finished both pours at around 11. Both pours went good, Made cylinders for both walls